Progress to Date
August 2008
The new high school was completed in the Summer of 2008, and dedcated on August 18 -- the first day of school. Designed by teacher Clint Lafollette and students Liam Holland and Ethan McGroom, the astrolabe, an ancient device relating to the planets and time, freezes the time and date of the high school dedication - 3 p.m. Aug. 18, 2008. Behind the clock are names of more than 150 donors, giving in excess of $5,000 each to the project.
August 2007
In
the spring, students began occupying the third floor of the three-story
ORHS Learning Center, consisting of science labs, media center, math
and social studies classrooms. The two historic round buildings were
demolished during spring break. The new Wildcat Arena gymnasium was completed before the beginning of the 2007-2008 school year. During
the summer, the Learning Center’s first and second floors were
completed, the old gym refurbished, the new Food Court was constructed,
and A Building classrooms were enlarged and completely renovated.
|
updated 8/13/2007
December 2006
The ORHS construction project continues along on schedule and within
budget. The new three story Learning Center, consisting of science
labs, media center, math and social studies classrooms and special
student and teacher work areas is progressing well. The top floor of
that Center will be available for occupancy during Spring Break of
2007, when the two historic Round Buildings on campus are demolished,
and those students moved into the new building. The roof
girders of the new Wildcat Arena gymnasium are being installed
now, so that the size and look of that facility is now easily
discernable. The Arena will be available for use before the end of this
school year, and will serve as the rain backup location for graduation,
in fact! The summer construction season will be extremely busy, with
completion of the first and second floors of the Learning Center,
refurbishment of the old Gymnasium building, renovation of major
portions of the existing A Building classrooms, and construction of the
new Food Court. The impacts of Donor's dollars are readily evident
at the ORHS campus now! Come by and see.
The focus of construction right now is on three basic portions of
the job. First, preparations are being made for startup of the
geothermal heating system, which must be ready for operation at the
time of demolition of the failing portion of "Old A". Messer is getting
the new HVAC connections ready, temporary boiler installed, and the
piping/pumps installed with the geothermal well network. Second, that
portion of "Old A" that is to be torn down (over Spring Break) is being
prepared for that demolition. That includes closing off the separation
wall in classrooms and hallways before demolition, conducting
hazardous material abatement (removal), and installation of a new exit
stairway. Once those preparations are done and the HVAC system readied
for changeover, the knock-down of "Old A" can be done and classes
continue as normal. Third, site grading and drilling is underway at the
area of the new Learning Center, in preparation for foundations to be
installed.
That work will move to the New Gym area once "Old A" portion is gone,
and also to the New Cafeteria area next to the Auditiorium. This
grading and drilling work will continue for several months.
This list of 9 items is the major contracted services completed to date.
- Owners Representative Heery contract September 14, 2004
- Architect Design with DLR September 14, 2004
- Topography and site surveys completed September 24, 2004
- Geothermal wells soil borings completed October 29, 2004 and May 13, 2005
- Traffic Impact Study November 11, 2004
- Commissioning agent April 14, 2005
- Pre-Grading Package with Messer Construction - June 7, 2005
- Hazardous Materials design specifications October 14, 2005
- Construction Contract with Messer Construction February 1, 2006
Some of the things that have occurred and are occurring now and in the near future are:
- December 19, 2005: Site clearing: removal of trees and relocation of soil.
- January 23, 2006: Temporary bus loop and Staff parking/student drop-off area.
- February 9, 2006: Drilling of the foundation piers for the new Learning Center.
- March 1, 2006: New gym sub grade preparation
- March 20, 2006: Demolition of building A
- April 6, 2006: Drill foundation piers for new gym
- March 1, 2006: Grading for new Oak Ridge Turnpike Parking Loop.
- May 9: 2006: Paving and curbing for new bus loop.
- April 11, 2006: Foundations work for new Kitchen area and Student dining.
Thank you to everyone that made this happen.
Mid December 2005 - The Oak Ridge Public Schools Education
Foundation has made its first contribution to the City to support the
rebuilding and renovation of Oak Ridge High School. The $337,041
contribution will begin to repay
the estimated $8 million that the high school project is receiving from
Qualified Zone Academy Bonds, a federal program of taxable bonds issued
by the Tennessee School Bond Authority. The Foundation has raised
$7,666,651.00, nearing its goal of $8 million.




